Projects Portfolio
Site preparation for Qatar Aluminum smelter and power plant

Location: Mesaieed, Qatar
Client: Qatar Aluminum (QATALUM)
Value (USD): 34,000,000
Completion: December, 2008

Project Scope:
This project involved site clearance, scarification and compaction of existing ground as well as placing and compaction of 5,000,000 m³ of fill materials for the platform construction of the aluminum smelter and power plant located in Mesaieed. The scope includes ground improvement using dynamic compaction for the carbon plant, removal of existing security fencing, installation of 8,000m of new security palisade fence around the perimeter of the aluminum and power plant.

 

(Ref#287)